[evlatests] [Fwd: Semi annual test/inspection of the EVLA Correlator room’s FM-200 system]
James Sullivan
jsulliva at nrao.edu
Wed Feb 25 15:56:48 EST 2009
All,
The semi annual test/inspection of the EVLA Correlator room’s FM-200
system and the Ana Laser II has been completed. The test/inspection was
conducted
around 11:00 AM. There were no problems found during the
test/inspection. The electrical shunt trip was not tested. The
test/inspection was conducted in accordance with the testing/inspection
requirements listed under NFPA 72 and 2001.
Thanks,
James B. Sullivan
NRAO-NM Safety Officer
Environment, Safety and Security Divisions
Phone: (505) 835-7344
Mark McKinnon wrote:
> Reminder from James Sullivan. Testing of the FM200 fire suppression
> system in the new correlator shielded room will occur tomorrow (Wed,
> Feb 25) at about 9am.
>
>
> -------- Original Message --------
> Subject: Semi annual test/inspection of the EVLA Correlator room’s
> FM-200 system
> Date: Fri, 30 Jan 2009 15:03:59 -0700
> From: James Sullivan <jsulliva at aoc.nrao.edu>
> To: Mark McKinnon <mmckinnon at nrao.edu>, Doug Gerrard
> <dgerrard at nrao.edu>, Mike Revnell <mrevnell at nrao.edu>, Eugene
> Cole <ecole at nrao.edu>, Bob Broilo <bbroilo at nrao.edu>, Guy
> Stanzione <gstanzione at nrao.edu>
> CC: Peggy Perley <pperley at nrao.edu>, Lew Serna <lserna at nrao.edu>,
> Steve Durand <sdurand at nrao.edu>
>
> All,
>
> It is time to prepare for the semi annual test/inspection of the EVLA
> Correlator room’s FM-200 system and test/inspection of the Ana Laser II
> system? The test/inspection will be conducted in accordance with the
> testing/inspection requirements listed in NFPA 72 and 2001.
>
> *(A.)* The following is a list of the items to be tested and/or
> inspected, but should not be considered complete.
>
> Test control panels for proper operation
> Complete function test of all modules.
> Test the emergency switch over from AC power to battery
> power.
> Test battery condition (clean cables and connections).
>
> Inspect all suppression cylinders for proper PSI and agent weight.
>
> Inspect all hoes, nozzles, and piping.
>
> Visually inspect agent area for unsealed penetrations and room integrity
>
> Test Ana Laser II system for proper operation.
>
> Test all smoke detectors, manual releases, rest (abort) buttons and any
> other component of the system that falls into the inspection
> requirements of the NFPA.
>
> Upon completion of the inspection a report of the findings will be
> provided to the NRAO safety officer or his representative.
>
> *(B.)* The following are the procedures that will be followed during
> the testing and inspection process.
>
> B.1. Disable GCA’s at tanks, inside and outside of Correlator room.
>
> B.2. Inspect all suppression cylinders for proper PSI and agent weight
>
> B.3. Engage the disable / maintenance by-pass switch
>
> B.4. Test control panels for proper operation
> Complete function test of all modules.
> Test the emergency power switch over (AC power to battery
> power).
> Test battery condition (clean cables and connections).
>
> B.5. Inspect all hoes, nozzles, and piping
>
> B.6. Test all devices- under floor and above
> Smoke detectors,
> Manual releases,
> Rest/abort buttons
>
> B.7. Test Ana Laser II system
>
> B.7. Inspect agent area for unsealed penetrations and room integrity
>
> B.8. Re-enable GCA’s
>
>
> The electrical shunt trip at this point will not be tested during
> this semi annual test/inspection, but plans for the accidental tripping
> of the shunt should be visited. I have requested a meeting concerning
> this semi annual test/inspection on 10-February-2009 @ 2:00 PM. I
> submitted request for AOC conference room 280 and VLA video conference
> room. I am planning to conduct the testing and inspection on
> 25-February-2009.
>
> Best Regards,
>
> James B. Sullivan
> NRAO-NM Safety Officer
> Environment, Safety and Security Divisions
> Phone: (505) 835-7344
-------------- next part --------------
A non-text attachment was scrubbed...
Name: jsulliva.vcf
Type: text/x-vcard
Size: 146 bytes
Desc: not available
URL: <http://listmgr.nrao.edu/pipermail/evlatests/attachments/20090225/f23a566b/attachment.vcf>
More information about the evlatests
mailing list