[mmaimcal]Fwd: ATF De-scoped downconverter [wbrundag at aoc.nrao.edu]
Al Wootten
awootten at cv3.cv.nrao.edu
Wed Apr 3 07:54:26 EST 2002
That is my understanding also. Owing to antenna lateness, something
must go to stay on schedule. We'll be doing interferometry with the
pre-prototypes (various groups have various names for this equipment but
I think this name best describes it.
Al
Brian Glendenning wrote:
> As I understand it, interferometry (and spectroscopy - no test correlator)
> is very likely to be posponed until after 2004-01-01, and will take place
> generally with pre-production prototypes rather than evaluation systems. So,
> for example, the test correlator would never be used, instead the prototype
> correlator would be the first correlator used at the VLA site. The intention
> would be to still do interferometry at the VLA after the antenna technical
> report is written.
>
> I'm not too sure of the schedule (would it be 2004-01-02, or would it be
> noticeably later) though.
>
> Cheers,
> Brian
>
> Since nobody ever remembers:
> test correlator = "GBT clone" correlator, available now
> prototype correlator = ALMA baseline correlator prototype, populated for 1
> baseline, due mid-03
>
>
>
> _______________________________________________
> mmaimcal mailing list
> mmaimcal at listmgr.cv.nrao.edu
> http://listmgr.cv.nrao.edu/mailman/listinfo/mmaimcal
>
More information about the mmaimcal
mailing list