[mmaimcal] forwarded message from Larry D'Addario

Al Wootten awootten at nrao.edu
Tue Feb 22 09:31:45 EST 2000


Dear Imcalers:

The System PDR and the Test Interferometer PDR are next week.  Please review
the materials and give comments to Jeff Mangum or to me.

Larry's list of readings:
RECOMMENDED READING LIST

ALMA SYSTEM DESIGN PDR 

Requirements and Standards

  http://www.tuc.nrao.edu/~ldaddari/rcvrSpecs.txt
  http://www.tuc.nrao.edu/~ldaddari/loSpec.txt
  http://www.tuc.nrao.edu/~ldaddari/phaseSpecs.txt

Block Diagram and Baseline Design

  http://www.tuc.nrao.edu/~ldaddari/alma.pdf	;block diagram, 10p.
  (Note that pages 1-7 are B size and are not very readable if reduced
  to A or A4.  Pages 8-10 are A size.)

  http://www.tuc.nrao.edu/~ldaddari/loPlan.txt
  This file should be on hand when studying the LO parts of the block
  diagram.  It explains the frequency conversion scheme for each band.

Major Design Decisions Taken

  http://www.tuc.nrao.edu/~ldaddari/ifband.txt
  Memo summarizing discussions of choice of 4-12 GHz for the 1st IF,
  with copies of all relevant email attached.

  http://www.tuc.nrao.edu/~ldaddari/loBaseline.txt
  Pros and cons of various LO options considered, with the reasons
  that the present baseline ("millimeter wavelength reference" option)
  was chosen.

Alternative Designs -- different IF and baseband bandwidths

  http://www.tuc.nrao.edu/~ldaddari/bandwidthIdea.txt
  
Timing and Synchronization

  http://www.tuc.nrao.edu/~ldaddari/timing.txt

Fringe Rotation, Phase Switching and Related Issues

  http://www.tuc.nrao.edu/~ldaddari/memo287.pdf
  Advance copy of ALMA memo, in distribution this week.

Power Distributon

  http://www.tuc.nrao.edu/~ldaddari/dcpower.txt


TEST INTERFEROMETER CDR

All material is still in the Test Interferometer Project Book, which
continues to get minor updates:

  http://www.tuc.nrao.edu/~demerson/almapbk/test_int/ .


--Larry



More information about the mmaimcal mailing list