[mmaimcal] forwarded message from Larry D'Addario
Al Wootten
awootten at nrao.edu
Tue Feb 22 09:31:45 EST 2000
Dear Imcalers:
The System PDR and the Test Interferometer PDR are next week. Please review
the materials and give comments to Jeff Mangum or to me.
Larry's list of readings:
RECOMMENDED READING LIST
ALMA SYSTEM DESIGN PDR
Requirements and Standards
http://www.tuc.nrao.edu/~ldaddari/rcvrSpecs.txt
http://www.tuc.nrao.edu/~ldaddari/loSpec.txt
http://www.tuc.nrao.edu/~ldaddari/phaseSpecs.txt
Block Diagram and Baseline Design
http://www.tuc.nrao.edu/~ldaddari/alma.pdf ;block diagram, 10p.
(Note that pages 1-7 are B size and are not very readable if reduced
to A or A4. Pages 8-10 are A size.)
http://www.tuc.nrao.edu/~ldaddari/loPlan.txt
This file should be on hand when studying the LO parts of the block
diagram. It explains the frequency conversion scheme for each band.
Major Design Decisions Taken
http://www.tuc.nrao.edu/~ldaddari/ifband.txt
Memo summarizing discussions of choice of 4-12 GHz for the 1st IF,
with copies of all relevant email attached.
http://www.tuc.nrao.edu/~ldaddari/loBaseline.txt
Pros and cons of various LO options considered, with the reasons
that the present baseline ("millimeter wavelength reference" option)
was chosen.
Alternative Designs -- different IF and baseband bandwidths
http://www.tuc.nrao.edu/~ldaddari/bandwidthIdea.txt
Timing and Synchronization
http://www.tuc.nrao.edu/~ldaddari/timing.txt
Fringe Rotation, Phase Switching and Related Issues
http://www.tuc.nrao.edu/~ldaddari/memo287.pdf
Advance copy of ALMA memo, in distribution this week.
Power Distributon
http://www.tuc.nrao.edu/~ldaddari/dcpower.txt
TEST INTERFEROMETER CDR
All material is still in the Test Interferometer Project Book, which
continues to get minor updates:
http://www.tuc.nrao.edu/~demerson/almapbk/test_int/ .
--Larry