[mmaimcal] Re: Science & System Work Program

Al Wootten awootten at nrao.edu
Tue Oct 19 10:31:03 EDT 1999


Stephane, John, and others

Our Imaging and Calibration group discussed this yesterday and came up with several good suggestions.
I played with these overnight and came up with the following revision.  The dates still need a lot of
work, as do people assignments etc.  A few names and dates are sketched in.  In this text version
some descriptions are shortened by the length of the available field.  A worksheet version may be
found in anon ftp to ftp.cv.nrao.edu then cd to /pub/NRAO-staff/awootten/mma/almawbs2.wq1
Changes mostly include moving items to more appropriate locations, including some reviews from the
MMA WBS and adding a few items which we thought missing.

    WBS#          Description                       Responsible            MMA-WBS       Start       Stop
    10            Science                                                              
    10.1          Scientific requirements           
     10.1.1       Overview                          A.Wootten S.Guilloteau                01-Jun-98  31-Dec-2001
     10.1.2       Prioritization of the frequency ba                                      01-Jun-98  31-Dec-2001
      10.1.2.1    35 GHz Scientific rationale       P. Cox, S. Myers                      01-Jun-98  31-Dec-2001
      10.1.2.1.1  Impact on receiver -- cost -- feas                                      01-Jun-98  31-Dec-2001
      10.1.2.1.2  Impact on LO system -- cost -- des                                      01-Jun-98  31-Dec-2001
      10.1.2.1.3  Comparison with existing or planne                                      01-Jun-98  31-Dec-2001
      10.1.2.2    Higher Frequency Bands Scientific rationale, incl 1500 GHz              01-Jun-98  31-Dec-2001
      10.1.2.2.1  Required bandwidth for each band                                        01-Jun-98  31-Dec-2001
      10.1.2.2.2  Impact on receiver -- cost -- feas                                      01-Jun-98  31-Dec-2001
      10.1.2.2.3  Impact on LO system -- cost -- des                                      01-Jun-98  31-Dec-2001
      10.1.2.3    Possible limitation on the Baselin                                      01-Jun-98  31-Dec-2001
      10.1.2.4    Comparison with existing or planne                                      01-Jun-98  31-Dec-2001
     10.1.3       Data flow and archiving specificatScience Software Requir               01-Jun-98  31-Dec-2001
      10.1.3.1    Define data rates (min.typical max                                      01-Jun-98  31-Dec-2001
      10.1.3.2    Define archiving policy (raw data                                       01-Jun-98  31-Dec-2001
      10.1.3.3    Define standard pipeline                                                01-Jun-98  31-Dec-2001
      10.1.3.4    Define non-standard modes                                               01-Jun-98  31-Dec-2001
      10.1.3.5    Quick-look specification          NRAO / IRAM                           01-Jun-98  31-Dec-2001
      10.1.3.6    Automated quality assessment methoNRAO / IRAM                           01-Jun-98  31-Dec-2001
    10.2          Site Characterization and MonitoriS.Radford/Nyman                       01-Jun-98  31-Dec-2001
     10.2.1       Atmospheric Stability                                    11.1.2         01-Jun-98  31-Dec-2001
     10.2.2       Atmospheric Transparency                                 11.1.3         01-Jun-98  31-Dec-2001
     10.2.3       Physical structure of atmosphere                         11.1.4         01-Jun-98  31-Dec-2001
     10.2.4       Site Characterization Reviews                                           01-Jun-98  31-Dec-2001
      10.2.4.1    Initial site Characterization and Monitoring Review      11.1.6.1       11-Jan-99
      10.2.4.1    Mid-term site Characterization and Monitoring Review     11.1.6.2     31-Mar-2000
      10.2.4.1    Final site Characterization and Monitoring Review        11.1.6.3     30-Mar-2001
    10.3          Array design and Operation                                              01-Jun-98  31-Dec-2001
     10.3.1       Compact configuration design      US (Kogan, Yun) / Europ11.2.1         01-Jun-98  31-Dec-2001
     10.3.2       Discrete intermediate configuratioNRAO (Kogan, Yun)      11.2.2         01-Jun-98  31-Dec-2001
     10.3.3       Continuous intermediate configuratConway / Webster                      01-Jun-98  31-Dec-2001
     10.3.4       Long baseline configurations      NRAO (Kogan, Yun)      11.2.2         01-Jun-98  31-Dec-2001
     10.3.4.1     Topological constraints           Yun, Radford                          01-Jun-98  31-Dec-2001
     10.3.4.2     3 - 10 km                         Kogan, Yun                            01-Jun-98  31-Dec-2001
     10.3.4.3     Very long (>10km) baselines       K.Menten                              01-Jun-98  31-Dec-2001
      10.3.4.3.1  Scientific rationale                                                    01-Jun-98  31-Dec-2001
      10.3.4.3.2  Impact on receiver -- cost -- feas                                      01-Jun-98  31-Dec-2001
      10.3.4.3.3  Impact on LO system -- cost -- des                                      01-Jun-98  31-Dec-2001
      10.3.4.3.4  Possible limitation on the Baselin                                      01-Jun-98  31-Dec-2001
     10.3.5       Configuration Reviews
      10.3.5.1    Array Configuration Preliminary Design Review            11.2.3       31-Jan-2000
      10.3.5.2    Array Configuration  Design Review                                    31-Jan-2001  31-Dec-2001
     10.3.6       Subarrays - number and population
     10.3.7       Operating model                   NRAO / IRAM                           01-Jun-98  31-Dec-2001
                  Observing Modes                                                         01-Jun-98  31-Dec-2001
                  Scheduling                                                              01-Jun-98  31-Dec-2001
                  Reconfigurations                  Yun                                   01-Jun-98  31-Dec-2001
                  Calibration cycles                                                      01-Jun-98  31-Dec-2001
    10.4          Calibration                                                             01-Jun-98  31-Dec-2001
     10.4.1       Total power mode calibration      Richer / Emerson ?                    01-Jun-98  31-Dec-2001
     10.4.2       Amplitude calibration strategy                                          01-Jun-98  31-Dec-2001
      10.4.2.1    Develop system temperature calibra                                      01-Jun-98  31-Dec-2001
      10.4.2.2    Develop calibration techniques applicable to wide band backends (to ha  01-Jun-98  31-Dec-2001
      10.4.2.3    Amplitude Calibration Reviews
       10.4.2.3.1 Initial Review                                           11.3.3.4       07-Jun-99
       10.4.2.3.2 Mid-term Review                                          11.3.3.5     31-May-2000
       10.4.2.3.3 Final Review                                             11.3.3.6     31-May-2001
     10.4.3       Develop bandpass calibration strat                                      01-Jun-98  31-Dec-2001
     10.4.4       Develop polarization calibration s                                      01-Jun-98  31-Dec-2001
     10.4.5       Phase calibration strategy                                              01-Jun-98  31-Dec-2001
      10.4.5.1    Develop atmospheric modeling technButler                                01-Jun-98  31-Dec-2001
      10.4.5.2    Develop atmospheric measuring deviOVRO/NRAO              11.3.1         01-Jun-98  31-Dec-2001
       10.4.5.2.1 22 GHz devices.                   OVRO/BIMA/NRAO (Butler)11.3.1         01-Jun-98  31-Dec-2001
       10.4.5.2.2 183 GHz devices.                  UK (Hills)             11.3.1         01-Jun-98  31-Dec-2001
      10.4.5.3    Select optimal device and method                         11.3.1         01-Jun-98  31-Dec-2001
      10.4.5.4    Phase  Calibration Reviews
       10.4.5.4.1 Initial Review                                           11.3.2.1       08-Jun-99
       10.4.5.4.2 Mid-term Review                                          11.3.2.2     31-May-2000
       10.4.5.4.3 Final Review                                             11.3.2.3     31-May-2001
    10.5          Imaging Studies                                          11.4           01-Jun-98  31-Dec-2001
     10.5.1       Develop "easy to use" simulation tNRAO(AIPS++) IRAM/Demirm              01-Jun-98  31-Dec-2001
     10.5.2       Prepare test images               Butler                                01-Jun-98  31-Dec-2001
     10.5.3       Multi-scale deconvolution methods NRAO (Holdaway)/Demirm                01-Jun-98  31-Dec-2001
     10.5.4       Total power mode                  Richer / Emerson ?                    01-Jun-98  31-Dec-2001
      10.5.4.1    Evaluate Wobbling sub-reflector   Mangum                                01-Jun-98  31-Dec-2001
      10.5.4.2    Evaluate OTF atmospheric cancellatMangum, Butler                        01-Jun-98  31-Dec-2001
     10.5.5       Mosaicing                         All                                   01-Jun-98  31-Dec-2001
      10.5.5.1    Mosaicing observing strategies    Yun                                   01-Jun-98  31-Dec-2001
      10.5.5.2    Mosaicing reduction strategies    Yun                                   01-Jun-98  31-Dec-2001
       10.5.5.2.1 Mosaicing interferometric data                                          01-Jun-98  31-Dec-2001
       10.5.5.2.1 Mosaicing interferometric and total power data                          01-Jun-98  31-Dec-2001
     10.5.6       Image fidelity investigations     NRAO IRAM/Demirm                      01-Jun-98  31-Dec-2001
      10.5.6.1    Evaluate alternate route: large siEmerson                               19-Sep-91
      10.5.6.2    Evaluate alternate route: array of                                      01-Jun-98  31-Dec-2001
     10.5.7       Implications for Array design                                           01-Jun-98  31-Dec-2001
     10.5.8       Polarization imaging                                                    01-Jun-98  31-Dec-2001

Cieux clairs,
Al
+--------------------------------------------------------+
| Alwyn  Wootten   (http://www.cv.nrao.edu/~awootten/)	 |
| Project Scientist, Atacama Large Millimeter Array/US   |
| Astronomer, National Radio Astronomy Observatory       |        
| 520 Edgemont Road, Charlottesville, VA 22903-2475, USA |
| (804)-296-0329 voice             Help us build The ALMA|        
| (804)-296-0278 FAX               {>    {>    {>    {>  |
+----------------------------------^-----^-----^-----^---+



More information about the mmaimcal mailing list