[evlatests] Ant 18 passes test
Pat Van Buskirk
pvanbusk at nrao.edu
Thu Aug 17 09:58:26 EDT 2006
We checked 18 in operations during startup last night and it passed all
the tests we are able to do. Pointing and baselines still needs to be
done by Ken, and the operator reported that fringes were a little low at
X band.
Cheers,
Pat
Steven Durand wrote:
> Hi
>
> Antenna 18 has passed the electronics acceptance test. Receivers
> include L, C, Q, K, X band has slightly low switched power and FE will
> look into it. The full report is on some thing like
> Filehost/Techdocs/sysintegration./acceptance
> test/Acceptance_Test_18_Aug162006.doc
>
>
> X Band ALC TP SD
> A -3.7 5.9 1.1
> B -3.8 4.8 .98
> C -3.9 6.0 .95
> D -3.8 5.8 .94
>
--
I have never seen a man who could do real work except under the stimulus
of encouragement and enthusiasm and the approval of the people for whom
he is working.
Charles M. Schwab (1862-1939, American industrialist, businessman)
More information about the evlatests
mailing list