Last Thursday (6/6/2002), after several days of work
on the License Agreement, all of the paperwork including
the P.O. Req & the signed License Agreement for the
port of the Nucleus PLUS rtos & the networking software
finally went to Accelerated Technology.

Additionally, we are now giving them a date of July 8th
for the daughter board.

Based on the 7/8/2002 date for the daughter board, AT is
giving us a start date of 7/10/2002 for the port, and
a completion date of 9/4/2002.

In an attempt to better this date, if possible, AT will
start work on the rtos portion of the effort ASAP using
either one of our development boards or one of their
own (they now have two TC11IB Triboards in-house).
They have already secured a copy of the toolset.
Of course, they cannot work on the ethernet driver or
other network issues until we have the daughter board
to them.