[asac] ASAC report: timeline
Ewine van Dishoeck
ewine at strw.leidenuniv.nl
Tue Sep 18 03:57:06 EDT 2001
Dear ASAC members,
I trust that you got back safely to your homes, even a few days late.
Many thanks again to all of you for staying focussed under these
difficult circumstances, and for contributing to our productive ASAC
meeting and the ALMA science day.
I enclose below the timeline for the report, together with the people
responsible for the various sections. Please keep to these deadlines, since
the schedule is tight.
Remember that the next telecon is on WEDNESDAY October 10, at the usual time.
With best regards,
Ewine
***************************************************************************
Schedule ASAC report:
====================
- Copies viewgraphs, powerpoint presentations -> Ewine a.s.a.p.
(see also e-mail Peter Shaver)
- First drafts sections -> Ewine Sept. 24
- First complete draft -> ASAC Oct. 3
- Comments ASAC -> Ewine Oct. 9
- Final report to E-ACC Oct. 15
Schedule Science Cases for enhancements (Appendix ~10 p. + figures):
=======================================
- ACA science case -> Ewine Sept. 29
- Complete draft -> ASAC Oct. 8
- Comments ASAC -> Ewine Oct. 11
- Final report to E-ACC Oct. 15
***************************************************************************
Sections:
=========
- Project status, management (from minutes)
- Site issues, configuration: Booth, Bronfman, Sakamoto
- ACA simulations, science: Cox, Crutcher, Hasegawa, Welch
- Correlator: Bachiller, Scoville, Yamamoto
- Operations: Evans, Fukui, Wilson
- Software: Benz, Gurwell, Tatematsu
- Calibration, WVR: Matsuo, Richer, Wilson
- Polarization: Crutcher
- Receivers: Blake, vD, Nakai
- Antennae, test interferometer: Fukui, Walmsley, Welch
- ASTE, APEX: Kawabe/Yamamoto, Schilke