System Requirements Review (SRR) 1-Aug-2003
SE&I IPT will conduct a System Requirement Review early in September
2003. The goal is to get the ALMA top level requirements documents
approved. The SRR will review these documents for completeness,
contradictions, disagreements, errors and misinterpretations. At the
end of the SRR we should be confident that we understand fully what it
is we have to build.
The documents to be reviewed include:
Science Requirements document
System Requirements document
Sub-system Requirements documents
Engineering Requirements documents
External ICDs
Safety Documents
Product Assurance Requirements
An EXCEL file listing these documents is attached. There are still some
uncertainties in the ICD list which will have to be resolved.
The documents to be reviewed should be submitted to the ALMAEDM as part
of the document approval process. The schedule for the SRR is given
below. Documents needed for the antenna RFP need to be approved earlier
than other requirements documents.
15-Aug submit antenna RFP documents to EDM
25-Aug CCB approval of RFP documents
01-Sep submit remaining documents to EDM
19-Sep end of comment period
30-Sep document update complete
07-Oct CCB/SRR teleconference for approval
The membership of the review panels and details of the review process
will be distributed later. Questions and comments on the SRR should be
sent to both Sramek and Haupt.
SE IPT
Dick Sramek
Christoph Haupt
-------------- next part --------------
A non-text attachment was scrubbed...
Name: SRR Delivery Summary1.xls
Type: application/msexcel
Size: 47104 bytes
Desc: not available
URL: <http://listmgr.nrao.edu/pipermail/alma_na/attachments/20030801/85180d9a/attachment.bin>
More information about the Alma_na
mailing list