[mmaimcal] Meeting today

Al Wootten awootten at nrao.edu
Mon Mar 22 11:48:30 EST 1999


Our major exercise for today will be going over the schedule for the
cost of the USA only MMA.

MMA Imaging and Calibration Group

Agenda for meeting Mon, 22 March 1999 at 4pm EST.

Date: Mon, 22 March 1999

Time: 4:00 pm EST (2:00 pm Socorro, 2:00 pm Tucson)

Phone: (804)296-7082 (CV SoundStation Premier Conference phone).

Past minutes, etc on MMA Imaging and Calibration Division Page

Agenda

--------

Meeting Status - Wootten
Invites
Rooms
Congress

MMA Costing Exercise - Wootten
Last week we discussed the second generation 183 GHz phase correction system.
Bob has a Gantt chart which has us designing this by next Jan with 
prototype and demonstration by 2001/2002 Jan.  I don't know where we
could test this but I need to come up with a cost.  My plan is to assume
a single channel (cooled?) HFET with the 32 channel backend Harris is
building.  Do Simon or Min know how much this might cost.  I'll get a
backend cost estimate from Harris if I can.  Maybe Webber can estimate
how much a contract to assemble an army of these would be.  I'll try to
get from Douglas Bock or Jack Welch a cost for the two channel amplitude
cal, then guesstimate a contract cost for 36 of those.  We need estimates of
manpower needs during construction.  Presumably there will be some ImCal
work going on at the prototype antenna, and also imaging studies, phase 
correction algorithm studies, etc.  

Here are the tasks and schedules:
484 Calibration and Imaging 2241 days Mon 8/2/99 Thu 2/28/08 
 485 Radiometric Phase Design & Prototype 656 days Mon 8/2/99 Thu 1/31/02 
  486 Design 183 GHz Phase Monitor Radiomete 131 days Mon 8/2/99 Mon 1/31/00 
  487 Prototype 183 GHz Phase Monitor Radiome 262 days Tue 2/1/00 Wed 1/31/01 
  488 Demonstrate 183 GHz Phase Monitor Radio 263 days Thu 2/1/01 Thu 1/31/02 
 489 Production Fabrication of Phase Monitor Rad 783 days Sat 9/1/01 Tue 8/31/04
  490 Contract Subassembly Fabrication 783 days Sat 9/1/01 Tue 8/31/04 
   491 Radiometer & Local Oscillator 783 days Sat 9/1/01 Tue 8/31/04 
   492 Spectrometer 783 days Sat 9/1/01 Tue 8/31/04 
   493 Feed, Window, lens, instrumentation 783 days Sat 9/1/01 Tue 8/31/04 
   494 M/C Interface 783 days Sat 9/1/01 Tue 8/31/04 
 495 Assembly & Test 459 days Tue 4/1/03 Fri 12/31/04 
 496 Deliver Production Radiometers 524 days Mon 6/30/03 Thu 6/30/05 
 497 Integration in Receiver Package 1110 days Tue 7/1/03 Mon 10/1/07 
 498 Verification on-Site 956 days Thu 7/1/04 Thu 2/28/08 
 499 Production Fabrication of Dual-load Amp Cal 281 days Mon 6/3/02 Mon 6/30/03
  500 Contract Subassembly 281 days Mon 6/3/02 Mon 6/30/03 
   501 Machining 216 days Mon 6/3/02 Mon 3/31/03 
   502 Load Fabrication 281 days Mon 6/3/02 Mon 6/30/03 
   503 Motors, Servo 281 days Mon 6/3/02 Mon 6/30/03 
   504 M/C Interface 216 days Mon 6/3/02 Mon 3/31/03 
 505 Assembly & Test 130 days Mon 3/3/03 Fri 8/29/03 
 506 Integration on Production Antennas 1001 days Thu 4/1/04 Thu 1/31/08 
507 Imaging Studies & Project Support 1828 days Mon 1/1/01 Mon 12/31/07 
508 Imaging Algorithm Development 1828 days Mon 1/1/01 Mon 12/31/07

Report from Chajnantor - Butler

Configuration Studies- Kogan

----------------------------------------------------------------------

--------

Action Items 8Mar99

UPCOMING REVIEW: On or before 31 May 1999 we review results from the OVRO
and BIMA phase correction systems.

DECISION: 183 GHz or 22 GHz phase correction?

DECISION: Is a nutating secondary necessary?

DECISION: What is the effect of 1/f noise in the HEMT amplifiers of SIS
receivers upon our ability to combine total power and interferometric images
into a faithful representation of the sky?

MEETINGS: MAC meeting 14 Apr 1999 at noon. ------

--------

Travel

------

T. Helfer:

A. Wootten: 12-13 April 43m observing 28 May - 3 Jun AAS 5-9 Jun I99 9 - 13
Jun CSO

J. Mangum:

M. Yun:

B. Butler:

S. Radford: