hi Tim, Martin al.- we here at Green Bank are planning projects for
the next 8 weeks or so -- I've drafted a list of what I think we (the
Caltech Backend) will need to do that involves using Green Bank people
over the period Aug 15 - Oct 1. I am assuming the CDR is not in this
period, and probably not in Oct either.
There is no guarantee that all of these requests will get supported
but it is not unreasonable to expect. In any case can you let me know
if there are any specific items that I've missed, or if any items
shouldn't be there for some reason??
thanks,
Brian
Electronics Group
-Continued support for Caltech detailed design phase (advice & consultation)
Receiver Group
-Design for post-detector amplification circuit
-Continued support for Caltech detailed design (advice & consultation)
Software Group
-Review software & Documentation already provided; if significant
changes or additions will be needed, request them.
More information about the gb-ccb