[daip] Waiting for POSSM and BPLOT
Eric Greisen
egreisen at nrao.edu
Tue Apr 13 12:07:26 EDT 2010
Andy Biggs wrote:
> Hi Eric. Yes, the problem seems to be related to SOLINT. If this is zero
> then the task plots my baselines and stops when it's finished. When
> SOLINT equals anything else then it will ask you to continue even if
> there's nothing else to plot.
>
> I've probably never used SOLINT=0 and this case isn't explicitly covered
> in the explain file, but I see now that it takes all the data within
> TIMERANG and averages it. This is actually what I've generally been
> requiring, but I do often need to set SOLINT as well.
I guessed a smuch and think I now even have a solution for solint > 0
and solint < 0 in many if not all cases. Tomorrow's MNJ should fix this
in 31DEC10.
Thanks for bugging me a little - this sort of stuff irritates me too.