[Escoordminutes] ES Div. Coordination Meeting Minutes-May
Lew Serna
lserna at nrao.edu
Wed May 4 10:02:28 EDT 2011
Minutes for the ES Division Coordination Meeting held on Tuesday, May 3,
2011, at 10:30 am, in the LL CB conference room. Attending were Lew
Serna, Guy Stanzione, Ramon Gutierrez, James Sullivan, Jon Thunborg, Bob
Broilo, Brent Avery, Martin Lopez and Paul Savedra.
BUDGET ---FY 2011 M&S budget is $17K less than FY2010. Travel is also
cut by $7K. Remember to charge to the correct VLA (533XXX.XXX) or VLBA
(633XXX.XXX) account when writing your PO's. Antenna Mechanics should
use VLBA administrative account 633610.4626 for tools to stock the SC
maintenance container (Bin), not to exceed $7K. FD elevation bearing
job is funded. C Band funding is also available for the FD trip.
VLBA --MK Elevation bearing grease samples for the "EL synchro side"
bearing still show metal particles. Fewer metal flakes showing in the
monthly samples reported thus far probably due to flushing out of the
bearing with grease. FD Elevation bearing Encoder side was showing metal
particles as well and will be replaced on 5/17/2011-5/20/2011.
The VLBA C-Band project is underway Antenna Mechanic effort is expected
to install the new feeds. The prototype will be installed in PT by June
of 2011. Other installations will occur between June 2011 and June 2012.
FY 2011 TT Visits-- NL is complete, OV with C-band horn
(6/9/2011-6/15/2011), SC with C-Band upgrade (8/2/2011-8/11/2011) and PT
(schedule on double maintenance days). Tentative FY 2012 trips are KP,
MK & LA.
Foundation repairs were conducted last summer. The Rail joints were
found to be cracking. Bob replaced most of the joints at NL and replaced
bad ones at HN. An engineering effort to improve the rail joints is
underway and will be tried at PT this month.
KP will require one each wheel assembly to be replaced. A short shaft
should be used on the spare wheel since it will fit assemblies at all
sites. The spare will be complete as soon as the hub is in place.
Repair of the St. Croix Subreflector is close to completion.
MK dish panels that were damaged will need to be repaired for spares.
Brent will try and locate 1/16" aluminum sheeting on surplus for
material to repair panels.
SC TT Bin is inspected and certified for it shipment to SC. The Bin
should be outfitted with tools before being sent in June.
AZ BEARINGS --6 new bearings have been delivered with a total of 7
bearings on hand. One bearing will be marked as the emergency spare.
Older grease samples show that antennas 25, 10 and 20, are candidates
for scheduled bearing changes. Antenna 25 is scheduled to get a new AZ
bearing on 8/25/2011. An estimated three weeks in the AAB are required
before a bearing change can occur. Parts from the bearings removed from
antennas are needed for measuring and fitting of new parts and should be
stored until they are scheduled to be shipped for repair. Fourteen
bearings have been replaced to date. It is desirable to send bearings
for refurbishment after about 3 bearings are available to send. Matt
Evatt will be trained as a bearing change supervisor.
PROJECTS:
CONTROL BUILDING STAIRWAYS---The CB balcony stairways will be replaced
with an improved design conforming to ADA. A new concrete landing will
have to be poured at the base of the eastern stairway and the stairway
replaced. The eastern stairway is barricaded to prevent its use. Work on
the eastern stairway has begun and should be completed in a couple of months
ST Croix PAINT---a crew was sent to St. Croix in April 2010 to continue
brush painting the areas where bleed through is evident. All new paint
is holding up well. A follow up painting program at SC would cost around
$17K per visit. The site techs are doing some painting spot repairs
until enough yearly funds are made available for regular follow up
painting trip. Some touch up and corrosion repairs will be done during
the SC TT trip this year if possible. Need to have more paint delivered
to prepare for this.
VLA ANTENNA FOUNDATION MOVEMENT--- Problems with north arm antenna
foundation movement needs to be investigated. It appears that the two
rearward station pillars have been slowly separating over the years at
CN5, CN6, CN7 and BN5 with BN5 being the worst. They have separated far
enough in about 33 years that 1 bolt (one on a reward pad) can no longer
be used to secure the antenna pad to the foundation pillar. Modification
of the CN5, CN6, and CN7and BN5 plates are complete and the plates are
reinstalled. This will solve the immediate problem of setting down
antennas on these foundations. If the pillars are moving apart it is
felt that there may be no practical way of preventing the movement. It
is believed that if this is the case it would be more
desirable/practical to build an additional foundation next to the bad
ones. Another option is that if the pillar movement is very slow it may
be adequate to modify/redesign the mounting plates in order to make up
and correct for the movement. In any case it would be desirable to get
inspection of the foundations and a recommendation for action. A cost
estimate for an inspection has been requested to an outside firm.
Markers have been set for taking measurements to try and see which
pillars are actually moving and at what rate. No change has been
observed between loaded and unloaded measurements thus far. Recent
Measurements taken continue to show no movement. No measurements taken
in the last couple of months.
GENERATOR REPAIRS--- Minor leaks were noticed at the engine rear seals
and it is desirable to install a better fuel filtering system. This work
would cost around $12K and has been put on the funding wish list.
HOT WATER LOOP. A project is submitted to install a hot water loop using
Correlator waste heat: The difference between the summer load and winter
load is mostly due to heating (at least 300kW). However, even during the
coldest mornings the cooling tower is ventilating correlator waste heat
into the atmosphere. We already use some of the heat in the Control
Building, but by extending the hot water loop to other buildings, we may
be able to reduce our power demand. The WIDAR correlator will have an
even higher heat output to work with. This project mainly consists of
burying a hot water loop and using heat exchangers similar to what many
complexes of buildings use. Payback on this project could be as quick as
1 year. Bob Broilo will investigate and provide further information.
This project has the potential to save $250K/year on our power bill.
Fuel System---Diesel Tank / The diesel tank containment is upgraded to
meet state regulations. Outstanding items: finish O&M plan, set up
annual certified pressure tests, paint fuel lines and receive regulatory
required training for owners/operators. Modifications and upgrades to
the fuel dispensing system are recommended. Monitoring and removal of
dispensing pumps requiring Breakaway valves and solenoids installed by
certified installers is necessary. Hand railing also should be installed
(by NRAO).
Fire Alarm upgrade- The site fire alarm is in need for upgrade. It is
desirable to replace the Simplex system with a system that includes
audible alarms at all buildings and area alarm reporting to operations.
Upgrade would cost around $30K. This project is under consideration for
next year's "project funding".
VLA FRM's- After removal and inspection of the troublesome FRM on
antenna 24 it was determined that the FRMs are in good shape. So far it
does not seem necessary to remove the FRMs from the antennas to perform
overhaul maintenance on them. It may be desirable to remove and inspect
a second troublesome FRM and do another inspection to be sure removal
from antennas is not necessary (perhaps Antenna 28). Thus far two new
steel gears to replace aluminum gears that wear are going to be stocked
in the warehouse and replaced as they fail. This task can be performed
while the FRM is on the antenna.
Quad Leg Rust---one of Antenna 13's upper quad legs was found to have
rusted badly and repairs will be made. A thorough inspection of all
antennas for this and other structural elements will be made to
determine future actions.
Asbestos Abatement training---relevant personnel need to attend renewal
training.
The Tech Services 1mW Transformer and MD panel will be installed later
this year.
EVLA;
Civil---SEC has installed a new 3MW utility Transformer (on 10/22/10).
The re-closure (utility breaker) remains to be installed at a later date
as scheduled by SEC. A 3MW transformer to replace the 2MW Generator
transformer has been delivered. This transformer junction box was
damaged and needs repair. This transformer will be installed later this
year
Weather station tower- This task is complete. Instrumentation will be
installed by the Electronics Division with ES help.
EVLA Antennas--- Dry air system needs to be installed. Three units are
ready for installation. Most dry air parts are ordered.
Antenna 5 has received the 4th compressor retrofit (1 week).
SAFETY REPORT: J. Sullivan
Accidents:
There have been a total of 2 accidents and 7 incidents reported for
NRAO-NM year to date.
1 of these accidents is attributed to the ES Division. SO-2011-001 --
Shoulder injury
3 of these incidents are attributed to the ES Division SO-2011-002-IN --
Hit Roll Door with forklift;
SO-2011-004-IN -- Slipped & Fell on ice; SO-2011-005-IN --- Backing
incident GSA Pick-up
Site Safety Meeting:
There have been 3 monthly site safety meetings so far this year.
Jan-2011, A/I Reports and Investigation, 30 employees in attendees.
Mar-2011, Haz Com, 30 employees in attendees.
Apr-2011, Driving Safety, 28 employees in attendees.
VLBA Sites:
Working on replacing Halon Extinguishers at VLBA sites, during TT
visits. I would like to thank the members of the tiger team for their
help with the extinguishers.
Inspections:
During this month I would like to get the following inspections conducted
Emergency Lights,
Exits,
Eye washes & showers, (if time allows)
Continue working on the Harnesses and Lanyards inspection. I will need
help on the Antenna inspections.
I would like to thank, Matt Metevier and ED Morgan for their help with
the antenna inspections last Qt.
Emergency Services: EMS Qt training took place the 1st qt and is
scheduled for the 2nd qt for June 28th.
ANNOUNCEMENTS:
* Fiber installations within the Tech Services will begin soon. This
should help with computer updating issues.
* Self Evaluations due June 1.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://listmgr.nrao.edu/pipermail/escoordminutes/attachments/20110504/e5db62b5/attachment.html>
More information about the Escoordminutes
mailing list