[Escoordminutes] ES Division Coordination Meeting-Sept.
Lew Serna
lserna at nrao.edu
Wed Oct 1 13:51:25 EDT 2008
Minutes for the ES Division Coordination Meeting held on Tuesday,
September 30, 2008 at 10:30 am, in the LL CB conference room. Attending
were Lew Serna, Charley Chavez, Bob Broilo, Guy Stanzione, Gene Cole,
James Sullivan, Jim Ruff, Brent Avery, Ramon Gutierrez, Martin Lopez and
Jon Thunborg.
BUDGET —We begin FY2009 tomorrow. Spent accounts at 80% of your normal
allotment. Do not make major purchases for Track Material. No special
projects are funded except the SC. Maintenance Visit. VLBA Foundations
(BR,NL) and Generator Repairs are high on the wish list for FY2009.
PAN’s are expected prior to 10/17/08.
VLBA -- SC (October/November), MK (August tentatively), and KP (May or
June tentatively) are scheduled for this year (FY2009). A Mechanical
Visit to Los Alamos will need to be made during a double maintenance
day. Eric will come up with a task list for LA. St Croix will take an
extended mechanical maintenance visit from 10/27/08-11/14/08 to replace
Subreflector, Elevation Bearing, finish painting, install platform and
change out one Azimuth wheel assembly. Steve Aragon will be in charge of
the AAB during the SC maintenance visit. A more robust box to ship the
subreflector was fabricated. The HN subreflector is prepared and ready
for the SC installation and is shipped.
The Brewster and North Liberty foundations continue to degrade and will
require urgent repairs in the near future at an approximate cost of $15K
each. Foundation work has been placed on the funding wish list. MK dish
panels that were damaged were replaced. The damaged panels need to be
repaired for spares.
The warehouse has stocked remainder of Wheel assembly parts necessary to
replace all remaining original wheel assemblies.
We will continue in FY2010 with HN, FD and BR.
AZ BEARINGS – Four Bearings have been shipped to Rotek for repair. Only
1 of the four bearings was refurbishable. A second bearing inner race
will be touched up and the bearing will be reassembled. This will give
us a usable emergency spare but should not be considered for permanent
use and should be labeled “emergency spare only” as soon as it arrives.
A third bearing will need a completely new inner ring fabricated.
Scheduled delivery of the first two bearings is September-October of
2008. It is possible that the third bearing may be delivered sometime
between November and next summer. There is a 2 year minimum lead time
for new and refurbished bearings from Rotek. Other suppliers are being
investigated for cheaper bearings and quicker turnarounds/shorter
leadtimes.
Older grease samples show that antennas 10, 20, are candidates for
scheduled bearing changes. Grease samples of all VLA antennas have been
taken and will be analyzed to determine the status of VLA AZ bearings as
soon as possible to plan future replacements.
An estimated three weeks in the AAB are required before a bearing change
can occur. Parts from the bearings removed from antennas are needed for
measuring and fitting of new parts and should be stored until they are
scheduled to be shipped for repair.
PROJECTS:
CONTROL BUILDING STAIRWAYS— The Control Building Stairways are being
replaced due to their rapid deterioration. The stairways will be
replaced with an improved design conforming to ADA. The western stairway
is complete. A new concrete landing will have to be poured at the base
of the eastern stairway and the steps replaced. The eastern stairway
barricaded to prevent its use. There is no urgency for this project
since safety has declared that there is no need for this stairway as a
means of emergency egress. Work on the eastern stairway will continue as
the workload permits. No further progress.
ST Croix MAINTENANCE VISIT— St. Croix Antenna has undergone extensive
repair and painting work due to its severe corrosion problems. Work
began on September 10 through December 21 completing 99 % of the
painting. Some topcoat painting remains at the base of backup structure.
In addition the AZ Wheel Assemblies (2ea), the Subreflector and the
elevation bearing replacement work will be completed. Everything shipped
on 9/26/08 and work will occur on 10/27/08-11/14/08.
VLA ANTENNA FOUNDATION MOVEMENT— A problem with north arm antenna
foundation movement needs to be addressed. It appears that the two
rearward station pillars have been slowly separating over the years at
CN5, BN3 and BN5 with BN5 being the worst. They have separated far
enough in about 33 years that 2 bolts (one on each reward pad) can no
longer be used to secure the antenna pads to the foundation pillars.
Markers have been set for taking measurements to try and see which
pillars are actually moving and at what rate. The plates from BN5 have
been removed for modification in the machine shop. No change was
observed between loaded and unloaded measurements however we will
continue measuring throughout the year. It may be desirable to modify
CN5 plates at the same time as the BN5 plates are being modified to save
set up time.
GENERATOR REPAIRS— Minor leaks were noticed at the engine rear seals and
it is desirable to install a better fuel filtering system. A bearing on
the generator unit also should be replacement as a PM. This work would
cost around $15K and has been put on the funding wish list.
POWER MONITOR— Installation of the power monitoring equipment in the
Hatch gear took place on 9/19/08. Power monitoring on the internet is
still pending. The power monitoring equipment will very useful in
determining our power quality needs and will keep operations informed of
power status at all times. A hatch gear PM and transformer PM’s were
also done. A hatch switch was repaired and the Cafeteria Transformer has
a leaking terminal that will need repair and surge arrestors at DW9 will
need replacing. The power was returned by 3:30pm on 9/19/08. Areas of
the site will require power outages for making repairs. Dates tbd.
HOT WATER LOOP. A project is submitted to install a hot water loop using
Correlator waste heat: The difference between the summer load and winter
load is mostly due
to heating (at least 300kW). However, even during the coldest mornings
the cooling tower is ventilating correlator waste heat into the
atmosphere. We already use some of the heat in the Control Building, but
by extending the hot water loop to other buildings, we may be able to
reduce our power demand. The WIDAR correlator will have an even higher
heat output to work with.
This project mainly consists of burying a hot water loop and using heat
exchangers similar to what many complexes of buildings use. Payback on
this project could be as quick as 1 year. Bob Broilo will investigate
and provide further information.
ABOVE GROUND STORAGE TANK COMPLIANCE—Our Above Ground Storage (AST)
facility is lacking in several areas according to an inspection done by
the New Mexico Environment Department. An operation and maintenance plan
and several other issues need to be addressed to comply with new
Petroleum Storage Tank Bureau (PSTB) AST regulations. A meeting will be
held at 9:00 am on Wednesday 10/01/08 to determine plan of action.
EVLA;
Civil— Correlator Room: The stringent cleaning underneath the computer
flooring following the installation of High Speed cabling is complete. A
damp mop type cleaning every two weeks will be implemented and adjusted
according to need. Correlator entry restrictions are in effect. No one
will be permitted access unless working on the equipment. Booties must
be worn and anti static procedures followed. There will be a meeting in
November for PM inspection of the correlator room fire systems. The
Civil Construction WBS will be completed in FY2009. The only civil work
remaining is miscellaneous, minor tasks associated with infrastructure
in the correlator shielded room.
EVLA Antennas— Feeds: S-Band rings are being cut in preparation for
assembly on a schedule of 2 every 7 weeks. It is desirable to install as
many feeds as possible while in the AAB. Some S-band feeds will probably
need to wait until the antennas are back in for overhauls. The permanent
location for the Vertex Room smoke detector has been decided. The
Antenna Group must complete mechanical overhauls of antennas to meet the
retrofit schedule of a total of 23 antennas to the EVLA design in
FY2009. A total of 20 S-band (2-4 GHz) feed horns will be fabricated in
FY2009. The Ku-band (12-18 GHz) feed horns will also be fabricated in
FY2009.
In the event remaining VLA antennas are shut down after the 22nd EVLA
antenna is complete it would be desirable to remove power and complete
some of the outfitting tasks in the field for some groups.
SAFETY REPORT:
The North Arm French Drain will need Confined Space signage.
A meeting to address action items for EPA compliance concerning Above
Ground Storage Tanks is necessary and will occur on Wednesday 10/1/08.
Congratulations to the Electrical Group and employees that helped with
the recent power system upgrade and preventive maintenance. Job well done.
One accident on the Track Crew, but it is still unknown if this is work
related or personal medical.
Trash cannot be placed in the Tie Pit. Only Ties should go into the tie
pit all other trash must be thrown in the dump. Possible problem with
the dump concerning water standing.
Transporter noise test report is forthcoming. Hearing protection during
transporter operations will be recommended but not required.
Up-Coming training for site personal. Confined Space, Lockout-Tagout and
Bloodborne Pathogens. These are required training.
ANNOUNCEMENTS:
ETK Training (Electronic Timekeeping) Electronic Timekeeping— the ETK
schedule has slipped by over a month and we are limited on the amount of
people that can be put on during year end. Year end has impacted
everything. By October 20, a plan to put on as many major groups as
possible will be initiated. By about November 20, the balance of NRAO
North American Payroll should be on the system. Parallel testing will
continue beyond November 20th until everyone feels the product is stable
enough to warrant the elimination of the paper timesheet. The Antenna
Mechanics will be the one of the focus groups to begin using the ETK in
October.
OTHER:
Public Tours on October 4. PRA will be selling food (hot dogs,
hamburgers etc.) in the cafeteria. Judy Stanley is looking for
volunteers with simple demos for interaction with the public also in the
cafeteria. Volunteers please contact Judy Stanley.
More information about the Escoordminutes
mailing list