[Escoordminutes] Minutes for ES Div. Coordination Meeting -- March
Lew Serna
lserna at aoc.nrao.edu
Tue Apr 4 10:16:05 EDT 2006
Minutes for the ES Division Coordination Meeting held on Tuesday, March
28, 2006, at 10:30 am, in the LL CB conference room. Attending were Lew
Serna, Guy Stanzione, Ramon Gutierrez, Bob Broilo, Steve Aragon, Gene
Cole, Brent Avery and Charley Chavez.
BUDGET — The new budget allocations are on the latest (March) budget
report. Please review your projects to ensure you can still afford
them. There is money out of a special fund to refurbish 3 Az bearings
this year. EVLA’s contingency money is low. Everyone is asked to be
fiscally responsible in order to try and complete the EVLA without
sacrificing receiver installations.
VLBA TT Trips—Shipping the container to St Croix is extremely expensive,
so we propose to ship a container one way with all the parts needed to
repair the antenna and with tools needed for future tiger team visits.
The existing container is fairly beat up and should be replaced since it
may not be acceptable for shipping much longer. A new sea worthy
container should be purchased soon to make the trips from here on out.
Shipping costs for the container round trip is around $12K. Ramon
estimates the cost for tools and a container is around $22K. The tool
cost may be reduced by shipping some of the necessary tools in a box
each visit instead of purchasing these tools and keeping them at St. Criox.
J. Thunborg has returned from an inspection trip to the St Croix antenna
and has evaluate the antenna in preparation for future maintenance. An
extensive painting effort will be required at this site and will likely
occur in FY2007. Jon’s report is filed as Antenna Memo #62.
The 2006 VLBA schedule is to visit KP on May 16 -22, MK in July 19-26
and tentatively visit HN on September 20-27.
AZ Bearings-- Parts from the bearings removed from antennas are needed
for measuring and fitting of new parts and should be stored until they
are scheduled to be shipped to Rotek for repair. There are 2 good
Azimuth bearings on hand. One spare bearing should be maintained at all
times. Antenna 14, 16 & 18’s bearings will be shipped to Rotek for
possible refurbishment this year. There is an 8-9 week lead time for
delivery on a refurbished bearing.
Antenna 26’s bearing will be changed next and is scheduled to occur in
summer of FY2006 (possibly as early as May). An estimated three weeks
in the AAB are required before a bearing change can occur. Grease
samples show that antennas 26, 10, 20, are good candidates for the next
bearing changes. Bearing replacement will occur at a rate of one per
year in order to maintain the EVLA outfitting schedule.
NEW PROJECTS:
ACU Modification-- A new ACU that replaces the ACU in its entirety is
desirable. The new ACU would hopefully improve the position loop
response, improve reliability and replace the obsolete components in the
current ACU. A PLC (Programmable Logic Controller) based upgrade would
cost around $3K per antenna. EVLA has funded the prototype and design
work is ongoing. This remains a low priority project but if funding
becomes possible the priority may be elevated. No funding commitments
funding commitments have been made for retrofitting of antennas.
Control building Stairways—The Control Building Stairways will be
replace due to repeated unsuccessful attempts to prevent their rusting.
The stairways will be replaced with an improved design conforming to
ADA. Materials have been ordered and drawings are being sent to the
Machine Shop and the Weld shop for fabrication of parts. A new
concrete landing will have to be poured at the base of the eastern
stairway. The stairs will be repaired one flight at a time so the work
can be fit in along with EVLA work.
LWDA (Long Wave Development Array) — The University of New Mexico and
the Naval Research Laboratory are leading a research project called the
Long Wavelength Demonstrator Array, which will be installed within the
VLA site central square mile. ES Division has provided access to the
site and installed a fiber optic cable that will be connected to VLA’s
west arm trunk at CW7. No further work by the ES Division is planned at
this time. Fiber terminations at CW7 are complete and terminations at
the Control Building will be made by the fiber group. This project is
closed.
Fire Station- The new Fire truck will not fit inside the existing fire
truck bay. The fire truck should be kept indoors to prevent the
freezing of pumps. A new bay will be constructed for the Fire truck and
the ambulance will be kept in the old Fire truck bay. Construction of a
new bay is complete. This project is complete.
190 MHz Receiver System—The maximum support available from E/S Division
for cherry picker support is 8 hrs per week. An NRAO employee who is
knowledgeable in cherry picker operations or receiver installation must
be present at the antenna at the appropriate times for the installation
of the 190 MHz receiver. This project will be closed until further notice.
Transporter Axles – The transporter axles are exhibiting several cracks
which are being rubbed out to prevent propagation of the cracks. This
is a temporary fix as more cracks will eventually reappear. These axles
should be replaced in the next 10 years with axles made of a different
material and design to increase their life. They are currently lasting
about 12-14 years and were last replaced in 1992. There are 12 axles
per transporter and each axle will cost around $3K to replace. There is
one spare axle of the existing design available. A plan to purchase 3
newly designed axles per year to replace all transporter axles in 8
years time is being proposed. It is worthwhile to investigate the cost
of having these built up at one time by an outside shop.
The last two inspections of “repaired” axles (in service for about 2
years) revealed no cracks. We will continue to monitor these axles
before any action is taken.
VLBA Gearbox and Wheel Assy. One Wheel assembly is built, parts are
available for a second. The second will be built as time permits. Also
there should be enough spares to repair the spare VLBA Gearbox that has
been cannibalized. Brent Avery will check to see if the parts have
been expensed. If the parts have been expensed the gearbox should be
restored. Brent Avery will check the status of the parts in the warehouse.
Ballast Cars— Two ballast cars have been purchased through a special
fund at a cost of $16.8k each. The purchase of the ballast cars will
eliminate the need to run the high maintenance and costly dump trucks
for track work. The mechanical repairs to the two ballast cars have been
made and the cars are ready. This project is complete.
EVLA STATUS
Peter Napier took on a job with ALMA vacating the EVLA Project Leader
position. Mark McKinnon has accepted the position as the new EVLA
Project Leader. Mark’s operational duties will be split among various
Division Heads so that Mark can concentrate on the EVLA project.
Correlator Room-- Stanzione— work remaining is flooring, Electrical and
HVAC. Flooring should begin around April 10. Power Filters and
distribution panels need wiring. The Air Conditioning units need to be
installed after the flooring is in. A modification of the Shielded room
doors is being designed to prevent accidental injury to personnel during
the automatic closure of the doors.
EVLA Antennas: E Cole—EVLA Antenna 13 retrofit is complete and will be
moved to AW5 on Wednesday. EVLA Antenna 24 will move to the Master Pad
on Tuesday for its electronic outfitting and Antenna 26 will enter the
AAB for a bearing change and its EVLA mechanical outfitting. The plan
for EVLA outfitting is 5 antennas per year.
Gene will get together with Jim Ruff and others to resolve storage
issues for EVLA feeds.
SAFETY REPORT
Safety officer was absent (training seminar). There were two new
accidents in ES Division since the last report. EPA inspection was done
in March and a report from the agency will be sent to us. Repairs to
our fuel storage tanks will need to be made and inspection procedures
will have to be put in place. Waste oil tanks will need better
containment and a little better housekeeping will be required. Action
items will be made once the report arrives.
OTHER
BnA reconfiguration has been delayed by 2 days and will begin on May 17.
The work schedule for move crews is shifted to Tue – Fri on the week of
May 15.
ANNOUNCEMENTS:
Retirement Party for Joe Sanchez at the cafeteria on March 30, 2006 at
3:30 pm, please join us.
PEPS – Begin April 1
2005 PERFORMANCE EVALUATION PROCESS TIME LINE
May 1 Due date for employees to return the self-appraisal forms to
their supervisors with the appropriate sections completed. Supervisors
begin writing employee evaluations based on their observations, coworker
feedback, and the self-appraisal completed by the employee. Supervisor
reviews the draft goals for the coming year and modifies as appropriate.
June 1 Supervisor reviews completed performance appraisal forms with
division
head and receives approval. Supervisor begins scheduling and holding
evaluation meetings with employees.
June 31 Due date for all evaluation meetings to be concluded and
appraisal forms signed by the employee. Employees should be given
sufficient time (at least 24 hours) to review and comment on the
evaluation. Based on information provided by the employee, Supervisors
should make corrections and changes as appropriate.
July 5 All of the original completed and signed appraisal forms must be
forwarded to the appropriate Human Resources Office. A copy of the
signed appraisal should be provided to the employee.
More information about the Escoordminutes
mailing list